In its latest quarterly report, Paladin announces that commercial production is expected to be achieved during the September quarter with first production planned to be shipped out towards the end of the September 2009 quarter.
The mine was officially opened by the President of Malawi, His Excellency Dr Bingu waMuthariika on 17 April. Commissioning and optimisation of the uranium process circuits is ongoing and production ramp-up has commenced with the plant initially operating in an intermittent mode during this phase. It is anticipated that the plant achieve 60%-70% design capacity during the September quarter.
The report further states that final construction of the sulphuric acid plant is expected to be completed by late August with the remaining works now predominantly being the lagging and cladding of the completed acid process equipment, piping and vessels.
The construction workforce is being progressively demobilised with the intention of retaining several hundred Malawian workers for general landscaping and camp upgrade.
Detailed planning and scheduling of the earthworks for the lined decant pond and lift extension of the north wall of the tailing storage facility by the earthworks contractor has commenced with commissioning of the former planned in December 2009, prior to the next wet season.
The Malawi Government’s road building contractor has sealed the first 13km section of the M26 public road from the town of
access road is planned to start in the next quarter. Road access to site remains non-problematic.
Production
Albeit still very much in its commissioning and ramp-up phase, Kayelekera produced 34,600lb during the June quarter.
Mining
Open pit mining activities, operating on a single daily shift, continued to focus on pit development. Several benches are now developed and the ore body has been fully exposed across the width of the pit. A total of
223,200t of ore grading 1,195ppm U3O8 and 740,835t of waste were removed from the pit in this quarter with a total
of approximately 2.37Mt mined from the area since operations began in 2008. The mine is planned to go to a two
shift operation in July.
Process Plant
The Kayelekera processing plant is the first of its kind to be built outside
Exploration Activity
Resource extension drilling to the west of the Kayelekera open pit started in June. Currently 18 holes totalling 2,022m have been completed. Initial results indicate that the mineralisation continues to extend to the west. However, detailed studies of the completed drilling programme are needed to determine whether the mine life will be extended. Final results and a subsequent resource update are expected in the December quarter.
No comments:
Post a Comment